Yangxihe Cascade Hydropower Station, Yuanyang County(23.5MW,2*6.6+3*3.5)

•Entrusted by Yunnan Yuanyang Hongyuan Hydropower Development Co., Ltd(2012)
–Yangxihe third-cascade power station (3 x 3.5 MW, horizontal Pelton, water head 360m) , Put into operation in June 2012
–Yangxihe second-cascade power station (2 x 6.5 MW, horizontal Pelton, water head 400m), Put into operation in May 2016
•Project content
–One-stop Service from Installation, Debugging and Operation Management of Mechanical and Electrical Equipment

•Total  capacity :35.5MW(23.5MW has been put into operation).

Main Building of Yangxihe third-cascade power station

6 kV Switching Room of Yangxihe third-cascade Power station

Booster Station of Yangxihe third-cascade Power station

Main Building of Yangxihe second-cascade Power station

6 kV Switching Room of Yangxihe second-cascade Power  station

CCR of Yangxihe third-cascade Power station